Preparation of MV/LV Projects Enel Ceará

Frame contract jul-2021 – jun-2024 (36 months) Lote Sur- Enel Ceará, Brasil.

The consortium of which IM3 DO BRASIL is a part was awarded on 07/16/2021 in the Tender for MV/LV Project Design Services – south zone – Enel Ceará. This new contract is fundamental for the growth of Im3 in the Brazilian territory and reinforces the already consolidated association with the ENEL group.

 

This is a 36-month framework contract and is intended to increase Im3’s presence in the northeast region of Brazil. The headquarters of the contract will be established in the city of Juazeiro do Norte.

 

The services included in this contract are the preparation of conceptual, basic and detailed engineering projects for overhead and underground lines, and medium and low voltage substations, with voltage levels 34.5, 13.8, 0.38 and 0.22 kV.

The consortium assumes an important commitment to social inclusion consisting of hiring at least 10% of workers who have been unemployed for more than 3 months, and also employees that this is their first job in this type of service.

 

Activities: Data collection on the ground, topography, design, engineering, and budgeting, including procedures and permits, for projects of extension of medium and low voltage networks to attend to new primary or secondary connections, requests for power increases, relocation/withdrawal of networks, relocation/extension of underground networks, improvement of networks, new feeders, projects in DAT networks, among others.

 

Outstanding technology capabilities: LiDAR Surveying, Q-GIS, AppFonik.