In order to verify compliance with birdlife protection measures on the basis of Royal Decree 1432/2008, 160 km of lines belonging to Iberdrola Distribución’s 132 kV and 20 kV network were checked for the issues specified the Galician regional general directorate for energy and mines.
During verification in the field the necessary data were gathered to produce a technical document for each facility showing compliance with the above requirements and proposing necessary measures where the requirements were not met.